5 Putting into operation
44 Multivapor™ Operation Manual, Version E
5.6 Commissioning the Multivapor-Rotavapor edition
The T-piece is inserted between the condenser
and the receiving flask of the rotary evaporator
and fixed with the clip. The vacuum tube is con-
nected to the SVL 22 joint of the T-piece.
Fig. 5.28: Commissioning the Multivapor-Rotavapor edition
NOTE
As the system has to be closed in order to generate a vacuum, the vapor duct on the rotary evapo-
rator must be sealed with an empty flask during operation.
5.7 Functional test
Once all of described installation steps have been completed proceed with the following functional test
to correctly operate the instrument.
5.7.1 Vacuum tightness test
NOTE
The vacuum tightness test can only be carried out with a vacuum controller installed or when a pres-
sure measuring device (manometer) is installed between the pump and the Multivapor.
1. Start the instrument and adjust the desired rotational speed, e.g. position 8.
2. Apply a vacuum of a preset value, e.g. 100 mbar.
3. Stop the vacuum and measure the pressure increase p within 2 min.
4. The instrument is tight if p < 10 mbar within 2 min.
To tighten the instrument, proceed as follows:
1. Close the vacuum tube from the vacuum pump to the condenser and check the leak rate of the
pump. In case of a leak consult the operation manual of the vacuum pump.
2. Close the vacuum tube at the vacuum tube side of the condenser with a blind cap and check the
leak rate of the condenser assembly. In case of a leak check the seals of the vacuum tube and the
GL-14 caps. Grease the glass joints if necessary.
3. Close the conical adapters of the vacuum cover using the blank adapters. In case of a leak
exchange the seals of the ribbed vacuum tube and/or the O-rings at the conical adapters. In case
of chemically affected O-rings, change the material of the O-rings according to Table 3-5.
4. Verify the quality of the sample tubes. They must not be chipped.
5. Check if the seals for the tube adapters are sound and correctly placed. In case of a leak exchange